State 23 repair work begins

Work will start on a second state highway project in Sheboygan County this week, according to the Wisconsin Department of Transportation (DOT) regional office in Green Bay.

Crews will begin sawing and removing concrete and pouring new concrete patches this week on State 23 from County P to State 32.

The 15-mile project, which also includes interchange ramps to County C, State 67, and State 32, is expected to be completed in July.

Traffic will be controlled via various techniques including: shoulder closures, lane closures, or flagging. Access will be maintained to local businesses and residences.

In the meantime, work continues on State 67 in the city of Plymouth.

Grading for concrete sidewalk is scheduled to begin this week as well as sealing the concrete pavement joints. Weather permitting crews should be able to complete the concrete sidewalk and driveways for this portion of the project by week’s end. Additional grading will be performed to prepare the side road asphalt transitions which could be paved by the end of the week.

The 0.84-mile, $3.18 million urban reconstruction project from the Mullet River to Suhrke Road in the city of Plymouth is scheduled for completion in November.

This project involves the reconstruction of State 67 from the Mullet River to Suhrke Road, resurfacing and repairs to the Mullet River bridge, and water utility, storm sewer and sanitary sewer reconstruction along with new concrete pavement.

State 67 will be closed to through traffic during construction. Access to local businesses and properties will be maintained. The following detours for each stage are:

For stage one through late June, State 67 is closed from the Mullet River bridge to a point immediately west of the County C and Caroline Street intersection. Traffic is detoured using the following route: State 67 north: County PP east, County E north, County C west to North Street (right), Main Street (left) to State 67 (Caroline Street) and reverse for State 67 south.

For stage two from late June to November, State 67 will be closed from a point immediately west of the County C and Caroline Street intersection to Suhrke Road. Traffic will be detoured using County C and State 23.

Motorists are advised to use caution and remain alert when driving through any work zone.

All work is weather dependent.


Most recent cover pages:














Copyright 2009-2018 The Plymouth Review, All Rights Reserved

Contact Information

113 E. Mill St., Plymouth WI 53073
Local: 920-893-6411 Toll Free: 1-877-467-6591
Fax: 920-893-5505










Plymouth Historical Society